Finance 3310
Capital Budgeting
Lecture 8
I. Types of projects
a. definition of project
b. mutually exclusive
c. independent
d. replacement
II. Investment criteria
a. Net Present Value (NPV)
b. Payback, Discounted Payback
c. Accounting Rate of Return (AAR)
d. Internal Rate of Return (IRR)
e. Comparison of NPV and IRR
f. Profitability Index
Capital budgeting: The process of
analyzing investment in long term assets (projects). A better
description is strategic asset allocation, that is, how should
the company's resources be allocated.
1. Types of projects
Projects can encompass almost anything that involves
allocation of significant corporate resources. These may include
which product or service to offer, whether to buy a new machine,
or whether or not to buy a whole company. Referring back to our
picture of the firm, capital budgeting has to do with what assets
to put in the circle.
a. Project: is any potential real
investment opportunity. We want to distinguish real assets
from financial assets. Real assets create cash flows for
the firm. Financial assets, such as stocks and bonds, are claims
on the cash flows which are generated by the real assets.
b. Mutually exclusive: are projects such
that if one is accepted, the others cannot be accepted (can do
either, or, not both)
c. Independent: if projects are
independent, then acceptance or rejection of one project has no
effect on another (can do any or all).
d. Replacement: these projects examine
whether we should keep an existing asset or replace it with a new
one.
2. Investment criteria
Investment criteria are the methods or procedures by which we
decide whether to accept or reject a particular project.
Assume: R=12% and cash flows are:
Expected after tax cash flows
| year 0 1 2 3 4 |
project a ($10,000) 6,500 3,000 3,000 1,000 |
project b ($10,000) 3,500 3,500 3,500 3,500 |
a). Net present value: this method is precisely the same method we used to value financial assets. We first estimate the future cash flows associated with a project, and then discount those cash flows back to present values. The difference between the present value of the inflows and the present value of the outflows is called Net Present Value, or NPV for short. NPV also represents value added. The value of the company will change by the NPV amount.
If projects are independent, then the rule is to accept all projects which have a positive NPV. If projects are mutually exclusive, then the rule is to accept the project with the highest NPV. Note that this rule is consistent with the goal of maximizing the value of the firm.
We can define NPV as follows:
NPV = ![]()
where Cft = cash flow at time t and R = cost of capital. The above assumes the cash flow at time 0 is negative and other cash flows are positive. Cash flows can be positive or negative at any point in time, however.
Using the example above, NPV for project A and project B are
below:
Discounted cash flows
Time -------------------------------project A -------------------------project B
| 0 1 2 3 4 NPV |
(10,000) 5,804 2,392 2,135 636 967 |
(10,000) 3,125 2,790 2,491 2,224 630 |
If these projects were independent, then the firm would accept
or do both of them. If the projects were mutually exclusive, the
firm would accept project A.
b). Payback: involves calculating the
number of years it takes to recover the initial investment. To
compute payback, find where the cumulative cash flow
becomes positive.
Cumulative cash flow
| Time | Project A | Project B |
| 0 | (10,000) | (10,000) |
| 1 | (3,500) | (6,500) |
| 2 | (500) | (3,000) |
| 3 | 2,500 | 500 |
Both projects recover the initial investment in the third
year. To be more specific, we calculate the fraction of the third
year as follows:
Project A: 2 + 500/3000 = 2 1/6 yrs. Project B: 2 + 3000/3500 = 2 6/7 yrs
For independent projects the rule is to accept all projects
which have a payback less than some predetermined number. For
mutually exclusive projects, the rule is to accept the project
with the shortest payback.
Problems with payback:
1) Doesn't consider time value of money. Consider the
following two projects and assume R=15% and our payback criteria
is two years.
| Year | Long | Short |
| 0 | -250 | -250 |
| 1 | 100 | 100 |
| 2 | 100 | 200 |
| 3 | 100 | 0 |
| 4 | 100 | 0 |
Payback: 2.5 for the 'long' project 1.75 for the 'short' project
NPV: 35.50 for the 'long' project (11.81) for the 'short'
project
Besides ignoring the time value of money payback also ignores
cash flows which occur after payback. In effect the 'long'
project's payback of 2.5 above ignores the cash flow in year 4.
What is the effect on payback for project 'long' if the cash flow
in year 4 had been $10,000 instead of $100?
Some companies use payback however. The primary reasons are:
The time value of money problem can be solved by using
discounted payback. Discounted payback first discounts (finds PV
of) each cash flow, then calculates payback. A couple of comments
about discounted payback. First, any project that 'pays back'
using discounted payback will have a positive NPV. Thus, some
projects which do not satisfy an arbitrary payback cutoff but
have positive NPV's may be rejected. Secondly, since discounted
payback requires the same amount of information and steps as NPV,
why not just use the NPV rule?
c). Average accounting return: is equal to some
measure of average net income or profit divided by some measure
of average investment. T7.6 illustrates the method. The problems
with AAR are that a) it doen't consider the time value of money,
and b) it focuses on income or profit rather than cash flow. In
summary, it does not have any real economic meaning.
d). Internal Rate of Return (IRR): is that rate of return which causes the net present value of the project's expected cash flows to be 0. For independent projects the firm should accept all projects for which IRR exceeds the cost of capital. For mutually exclusive projects, the firm should select the project with the highest IRR.
In order to calculate the IRR you have to find the interest
rate which solves the following equation:
0 = ![]()
You might note that this is exactly the same formula we used
to calculate YTM if you substitute the price of the bond for CF0 and then move it to the left-hand side.
Therefore, just like YTM, there are two ways to solve for IRR:
1. Trial and error
Pick a rate and then calculate NPV:
if NPV > 0 ==> try a larger %
if NPV < 0 ==> try a smaller %
2. Financial calculator or spreadsheet
In example above:
Project b is easy to find ==> annuity w/ pv =10,000
Project b: IRR = 14.96%
Project a: try 15% ==> NPV = 465 > 0 ==>
larger %
try 16% ==> NPV = 307 > 0 ==> larger %
try 18% ==> NPV = 5 ==> approx. 18%
Independent => take both since IRR > cost of cap.
(18% and 14.96% > 12%)
Mutually excl. => take Project A, since irr is higher
(18% > 14.96%)
Business executives like IRR because they are accustomed to thinking about rates of return and intuitively understand comparing the return on a project with the cost of capital.
Since business people are accustomed to thinking about rates
of return, we should explore IRR a little further. It turns out
that when the cash flow stream is non-traditional, not a cash
outflow followed by several cash inflows, then IRR can give
several answers or can give a misleading answer. Since we know
NPV is always a correct criteria to use, we should compare NPV
with IRR.
e) Comparison of NPV with IRR
If projects are independent, then NPV and IRR are
mathematically equivalent and it does not make any difference
which rule you use. To see this, consider the formula for NPV:
NPV = ![]()
Suppose that when we plug in the cost of capital for R in the
above equation NPV is positive. We should do the project because
the present value of the benefits (cash inflows) exceeds the
present value of the costs (cash outflows). Now we want to
calculate IRR. By definition IRR is the rate that causes NPV = 0.
If discounting the cash flows at the cost of capital causes NPV
to be positive, then we need to discount at a higher rate to
cause the NPV to be 0. Therefore, whenever NPV is greater than 0,
IRR is greater than the cost of capital. The two rules are
equivalent.
Suppose instead that the projects are mutually exclusive. To
compare NPV and IRR in this case it will be useful to construct a
NPV Profile. A NPV Profile plots the NPV of a project at
different costs of capital.
[Picture to be provided in class.]
We can easily find three points for each project and then just
connect the dots. The intersection with the vertical axis is the
NPV when the cost of capital is 0. You simply add all the project
cash flows to find this point. We also know the NPV when the cost
of capital is 12%. We found previously that when the cost of
capital is 12% project A has a NPV of 967, while project B has a
NPV of 630. The intersection with the horizontal axis occurs when
NPV = 0, which is the IRR. Project A intersects the axis at a
rate of approximately 18%, while B intersects the axis at
approximately 15%.
There are a couple of other things to point out about this NPV profile. First of all, notice that the curve for project B is steeper than the one for project A. Recall that slope measures the 'change in y' for a given 'change in x.' Here we are looking at the change in NPV for a given change in R. Project B's cash flows are, on average, further away in time and hence are more sensitive to a change in the discount rate.
Secondly, note that for lower costs of capital, say 6%, project B has a higher NPV than project A. Thus, for a lower cost of capital NPV says choose project B, while IRR says choose project A. These are conflicting signals. We know from the previous discussion that NPV is always correct.
The reason IRR gives a different answer than NPV is a
technical one. IRR is the same calculation as YTM and like YTM
makes the same assumption about reinvestment of interim
cash flows. That is, IRR assumes that interim cash flows can be
reinvested at the IRR. NPV assumes interim cash flows can be
reinvested at the cost of capital.
A similar problem occurs when two projects involve a
difference in scale and IRR is used as an investment criteria.
Example: assume R = 10%
Project Y cost = 1,000; return = 2,000
Project Z cost = 100,000; return = 125,000
Project Y's IRR = 100% ; Project Z's IRR = 25%
Should we take project Y if mutually exclusive?
Project Y's NPV = 818 ; Project Z's NPV = 13,636
Project Z will add much more value to the firm. The problem
here is, what is going to be done with the other 99,000. IRR in
effect assumes the 99,000 can be invested at a 100% return.
Notice that we can divide project Z's cash flows into two
parts, one of which is the same as project Y:
Cost |
Return |
NPV |
IRR |
|
Y |
1,000 |
2,000 |
818 |
100% |
W |
99,000 |
123,000 |
12,818 |
24% |
Z |
100,000 |
125,000 |
13,636 |
25% |
Project Z is the same as doing project Y, plus some other project having an IRR of 24% and a NPV of 12,818. You would only choose project Y if you could invest the other 99,000 in something at least this good.
f) Profitability Index (PI) - is the present
value of cash inflows divided by the present value of cash
outflows. The PI gives a measure of 'bang per buck' or
profitability per dollar invested. For mutually exclusive
projects the rule is to take the project with the highest PI. For
independent projects, the rule is to take the project with the
highest PI. Note that whenever NPV > 0, the profitability
index is greater than 1.
For our initial project A the PI is 1.0967 and for project B
it is 1.063. For our last two projects Y and Z, the PI's are
1.818 and 1.12818, respectively.
The profitability index can also give misleading answers for
mutually exclusive projects, as indicated by project Y and Z. It
is true that the initial 1,000 invested is more productive or
profitable for project Y, but the total value added is higher for
project Z. PI is useful in situations involving capital
rationing.
Summary:
As your book indicates, most companies will use several of
these rules, though the trend has been toward NPV and IRR.